Camber over a 224-foot length
The bridge required precise elevation layouts and camber control throughout its length to establish the correct girder geometry.
Infrastructure & Transportation
Bridge steel detailing driven by elevation, camber and connection accuracy.
Project overview
The 2nd Avenue Grant County Bridge is located between Tioga Street and Walnut Street in Big Stone City, South Dakota.
The 224-foot steel plate girder bridge incorporates approximately 250 tons of structural steel. Working for TrueNorth Steel, Anatomic fully modeled and detailed the bridge structure using Tekla Structures.
The detailing required careful development of elevation layouts and bridge camber, along with precise representation of welded and bolted connections.
Approx. 250
Tons detailed
Enlarge view
Technical complexity
The bridge required precise elevation layouts and camber control throughout its length to establish the correct girder geometry.
Welded and bolted connections had to be modeled and detailed in relation to the bridge geometry, with accurate representation in fabrication drawings.
TrueNorth Steel’s specialized drawing requirements called for customized documentation developed from the Tekla Structures model.
Fabrication documentation
The complete bridge structure was modeled in Tekla Structures, providing a coordinated basis for fabrication and erection drawings.
The team adapted the drawing content and presentation to meet TrueNorth Steel’s specific requirements while maintaining consistency with the detailed bridge model.