DESIGN DETAILING

Denver International Airport

Complex steel detailing for two long-span diagrid canopies at Denver International Airport.

LocationDenver, Colorado
ClientMiro Engineers
Structural SteelMore than 2,300 tons

Project overview

Turning complex canopy geometry into fabrication-ready information.

The Denver International Airport Hotel and Transit Center project included more than 2,300 tons of structural steel across a new hotel, commuter rail platform and two architecturally distinctive steel canopies.

One canopy spans more than 120 feet above the train platform. The larger, approximately 205-foot canopy extends beyond both sides of the hotel and continues beneath the building, integrating with its supporting arches.

Both structures feature complex moment-welded diagrid systems. At the time, this was the largest project Anatomic had undertaken through the Design Detailing process.

Completed Denver International Airport station canopy with the Westin building behind it. More than 2,300 Tons detailed Enlarge view
Completed Denver International Airport station canopy with the Westin building behind it.
Project team and technical details
Engineer of Record
S.A. Miro, Inc.
General Contractors
Mortenson, Hunt, Saunders
Primary Scope
Structural steel detailing
Delivery Method
Design Detailing
Key Structures
Hotel, commuter rail platform and two long-span steel canopies
Structural System
Moment-welded diagrid

Model to field

From complex steel geometry to construction on site.

The coordinated structural model and construction photographs show the diagrid canopies taking shape, from their intricate steel framework to their integration with the hotel and rail platform.

Overall Denver International Airport structural visualization showing the Westin building and curved station canopy geometry.01 / Coordinated model
Overall Denver International Airport structural visualization showing the Westin building and curved station canopy geometry.
Overall view of the curved station canopy steel during construction at Denver International Airport.02 / Fabrication & field
Overall view of the curved station canopy steel during construction at Denver International Airport.

Technical complexity

Complex welded connections resolved before fabrication.

01

Congested welded diagrid joints

Many connections required complete joint penetration welds and multiple internal stiffeners, with several components meeting within confined spaces.

02

Skewed canopy geometry

Non-orthogonal member intersections created highly variable connection conditions that required individual detailing rather than repetitive standard solutions.

03

Welding access and constructability

Stiffener arrangements and intersecting members had to be reviewed with fabrication sequence, welding access and constructability in mind.

04

Hotel and canopy integration

The larger canopy extended beneath the hotel, requiring careful coordination of the diagrid framing with the arches supporting the building above.

Design detailing

Resolving complex connections through direct engineering collaboration.

The project’s Design Detailing approach brought Anatomic into direct coordination with the engineering team while connection details were being developed.

Using a shared 3D model, the teams reviewed congested diagrid joints, internal stiffener arrangements and difficult connection geometry before releasing fabrication information.

This allowed technical questions to be addressed collaboratively, reducing reliance on successive RFIs and helping maintain progress on the steel package.

Project animation

Explore the project in motion.

Project result

A coordinated result delivered ahead of schedule.

The collaborative Design Detailing process helped the project team address complex connection conditions more directly, reducing reliance on successive RFIs and supporting faster technical decisions.

We believe this approach contributed to the project being completed approximately six months ahead of schedule.

“The project was an exceptional success. Having the 3D model and collaboration available with the Tekla team was a great asset to the project. The schedule benefited greatly from having Miro carry the detailing contract.”

Joe Rapp — Engineer of Record, S.A. Miro, Inc.