Frequent drawing revisions
New drawing sets were issued throughout detailing, requiring the team to identify changes affecting the steel package.
INDUSTRIAL
Steel detailing within a continuously evolving design-build project.
Project overview
The Advanced Water Purification Facility is part of the Donald C. Tillman Water Reclamation Plant development in Van Nuys, California, intended to increase water reuse and groundwater replenishment capacity for the City of Los Angeles.
Working for S&S Steel Fabrication, Anatomic provided detailing for approximately 650 tons of structural and miscellaneous steel, including building structures and stairs.
The project’s design-build delivery required the team to work with frequently revised drawings and a high volume of RFIs.
Approx. 650
Tons detailed
Enlarge view
Design-build coordination
New drawing sets were issued throughout detailing, requiring the team to identify changes affecting the steel package.
Earlier RFIs, responses and design assumptions had to be reviewed against each new issue to confirm they remained valid.
Anatomic updated the Tekla model to reflect current documentation, coordinating changes closely with S&S Steel Fabrication.
Project animation