Institutional/Public

Theodore Roosevelt Presidential Library

Detailing a landmark library shaped by the North Dakota landscape.

LocationMedora, North Dakota
Client and FabricatorTrueNorth Steel
Structural SteelApproximately 698 tons

Project overview

A building designed to become part of its own interpretive story.

The Theodore Roosevelt Presidential Library is a distinctive library and museum in Medora, North Dakota, dedicated to the life and legacy of the former U.S. president.

Set into the surrounding landscape, the building is designed to become part of the visitor experience. Its architecture and sustainable building technologies contribute to the Library’s interpretive story, connecting the building itself with Theodore Roosevelt’s life and legacy.

Working for TrueNorth Steel, Anatomic provided structural steel detailing for approximately 698 tons of steel. A key requirement was extensive coordination between the structural steelwork and the glulam and wood suppliers.

Aerial photograph of the Theodore Roosevelt Presidential Library showing the landscaped roof and building within the surrounding terrain. Approx. 698 Tons detailed Enlarge view
Aerial photograph of the Theodore Roosevelt Presidential Library showing the landscaped roof and building within the surrounding terrain.
Project team and technical details
Engineer of Record
Magnusson Klemencic Associates (MKA)
Architects
JLG Architects & Snøhetta
General Contractor
JE Dunn Construction
Connection Design
MKA
Detailing Platform
Tekla Structures
Detailing Team
Approximately 8–12 people
Expected Project Completion
2026

Model to field

Connecting the detailed steel model with the completed building.

The project was detailed in Tekla Structures, providing a three-dimensional reference for coordinating structural steel with the building’s timber and architectural systems.

The model supported the review of steel geometry and connection locations and provided a basis for developing fabrication information.

Overall structural model of the Theodore Roosevelt Presidential Library showing its broad roof framing and curved perimeter.01 / Coordinated model
Overall structural model of the Theodore Roosevelt Presidential Library showing its broad roof framing and curved perimeter.
Sheltered outdoor space at the Theodore Roosevelt Presidential Library beneath a timber roof structure.02 / Fabrication & field
Sheltered outdoor space at the Theodore Roosevelt Presidential Library beneath a timber roof structure.

Technical challenges

Precision at every steel-to-timber interface.

01

Steel and glulam coordination

The project required extensive coordination with glulam and wood suppliers to align structural steel with the engineered timber systems.

02

Connection geometry and locations

Steel-to-timber interfaces required careful review of member geometry and connection locations to maintain alignment between the different structural systems.

03

Fabrication and installation requirements

Coordination also had to account for differences between steel and timber fabrication processes and installation requirements, helping identify potential conflicts before construction.

Project animation